top of page

Crossrail - Ilford Yard Stabling Project – Stage 1

Client: VolkerFitzpatrick Ltd
Value: £2.1 million
Duration: Aug 2014 – Jan 2016
 
Project Description

Ilford Yard Stabling Project was a £55 million project between VolkerFitzpatrick Ltd and Crossrail. This project covered the provision of additional stabling facilities at Ilford Depot.

 

As well as the provision of additional stabling facilities the project required changes to a number of existing buildings at the Ilford Yard to ensure that Crossrail can build ten new sidings to house trains overnight.

Work included the demolition of Workshop B, the existing Paint Shop, Mess Buildings and Shunters Cabin. A replacement Paint Shop and new Logistics and Stores building was constructed. Modifications to Bombardier Transportation Workshop A were also completed.

Main Scope of Work
Enabling Works for site offices
 
Bulk excavation of material and cart
off site
  • 1300 plus loads

Reinforced concrete strip foundations & pad foundations
  • 50.15 tonne of reinforcement

  • 2208 m3 of concrete

  • 428 no. holding down bolts

Laid over 5000m of:
  • Kerbs

  • Edging

  • Aco Channels

Install 2 no. pumping stations
  • Install 6.2 x 2.1m foul water pump station at a depth of 6.5 metres

  • Install 2.0 x 2.0 x 4.0m deep tank at a depth of 5.5 metres

Installed new vehicle crossing over railway track
  • Utilised our PTS operatives to breakout existing vehicle crossing
  • Installed new vehicle tarmac crossing under line possession and isolation
Drainage
  • 980m of drainage with pipe diameter up to 600mm

  • 34 no. manholes – maximum depth = 4.5 metres deep

Ducting
  • 6450m of ducting

  • 65 no duct pits

  • 750m of troughing

Rainwater Harvesting Tank
  • 7.0 x 2.0m RWHT installed at a depth of 3.5m deep

Attenuation Tank
  • 884m3 attenuation tank

Installed new Substation
  • Including excavation, shutter & pour of concrete and backfill complete

bottom of page